91 Refresh Project

Completed Construction

0622 91 Refresh Project

Status: Completed Construction

Location: Eastbound and westbound 91 between the Lincoln Ave Interchange and Interstate 15 in Corona

Type of Project: Highways

Location: Eastbound and westbound 91 between the Lincoln Ave Interchange and Interstate 15 in Corona

Construction: Summer 2022 to fall 2023

Investment: $12.6 million

OVERVIEW

The Riverside County Transportation Commission, in partnership with Caltrans, repaved lanes and made repairs to sound walls and associated concrete barriers along the outer portions of eastbound and westbound 91 in Corona. Work took place mainly between the Lincoln Ave interchange and Interstate 15, an area with a long history of roadway settlement. This work was part of an ongoing investment in the heavily traveled 91 corridor.

The “91 Refresh” work took place from summer of 2022 through the fall of 2023.


Interstate 15 Interim Corridor Operations Project

Completed Construction

0922 15 ICOP Photo

Status: Completed Construction

Location: Western Riverside County

Type of Project: Highways

Location: Southbound Interstate 15, Cajalco Road on-ramp to Weirick Road off-ramp

Construction: May 2022 to early fall 2022; lane opened July 2022

Investment: $5 million

OVERVIEW

The I-15 Interim Corridor Operations Project was the result of an agency task force led by staff from RCTC, Caltrans, the City of Corona, and the County of Riverside. The group began meeting in June 2021 to study alternatives and develop near-term improvements to help improve traffic operations. The CHP also provided input regarding safety and vehicle pull-over locations.

The project added a non-tolled lane to southbound I-15 between the Cajalco Road on-ramp and the Weirick Road off-ramp, a distance of just under one mile. To add the lane, crews strengthened the pavement of the outer and inner I-15 shoulders to handle traffic loads. Crews restriped the roadway to provide three 11-foot wide lanes, one 12-foot wide lane, a varying 3 to 8-foot wide outer shoulder, and a varying 2 to 5-foot wide inner shoulder. The new lane opened July 23, 2022.

Work began May 23, 2022, and the new lane opened on July 23, 2022. Closeout activities were completed in fall 2022.

RCTC completed engineering and environmental studies, as well as the project design, in early 2022. RCTC awarded a construction contract on March 9, 2022. Work began May 23, 2022, and the new lane opened on July 23, 2022. Closeout activities were completed in fall 2022.

For questions related to the Interstate 15 Interim Corridor Operations Project, please email info@rctc.org


Interstate 215 Placentia Avenue Interchange

Completed Construction

Status: Under Construction

Location: Western Riverside County

Type of Project: Interchanges

Location: I-215 Placentia Avenue, Perris

Construction: August 2020 to fall 2022

Investment: $42 million (construction)

OVERVIEW

The I-215 Placentia Avenue Interchange in Perris is the first construction project of the Mid County Parkway, a new 16-mile transportation corridor between the San Jacinto and Perris valleys. The Mid County Parkway is designed to reduce travel times between these areas. Please see the Mid County Parkway Ramona Expressway page for details about this corridor.

Designed to meet the needs of a growing population, the Placentia interchange project provides a new way to enter and exit I-215. The new interchange is located between Ramona Expressway to the north and Nuevo Road to the south. It was designed to improve access, traffic flow, and air quality by adding on-ramps and off-ramps to Placentia Avenue, realigning East Frontage Road, widening the Placentia Avenue overcrossing, and adding lanes to Placentia Avenue between Harvill Avenue and Indian Avenue.

Construction began on August 24, 2020 and the interchange opened fall 2022.

Construction began August 24, 2020 and the interchange opened fall 2022.

For questions related to the I-215 Placentia Avenue Interchange Project, please email info@rctc.org.


RIVERSIDE COUNTY METROLINK STATION IMPROVEMENTS

Completed Construction

Status: Under Construction

Location: Western Riverside County

Type of Project: Rail Station Improvements

Location: Riverside County Metrolink Stations

Construction: Various

Investment: Various

For questions related to these projects, email info@rctc.org

OVERVIEW

The Riverside County Transportation Commission (RCTC) owns and operates the Metrolink stations in Riverside County. Many improvements are being made to the stations to ensure riders have a positive experience.

See below for more information about each of the projects:

This project will address the needs of Riverside County commuters. Benefits and features include:

  • Capacity: Adding a second train platform and lengthening the existing train platform to accommodate the length of Metrolink’s standard six-car trains. This will allow for service improvements on the 91/Perris Valley Line — both peak service and reverse commute service to and from adjacent counties — as well as improved service reliability within Riverside County. The project also will upgrade 2.5 miles of track that are part of a future nine mile double-track corridor south of the station.
  • Traffic Flow: Reducing traffic congestion on Interstate 215 by providing efficient and reliable public transit options for Riverside County residents who have some of the longest commutes in southern California.
  • Clean Air: Reducing auto emissions by encouraging more residents to commute by train.

Construction is expected to begin in fall 2022 and be completed by spring 2024.

Click here to view the project fact sheet. 

This project will expand the Metrolink train layover facility at the Riverside-Downtown Station. The project will allow more trains to be housed at the station at the end of each night shift, which will allow for more efficient service.

Work began in March 2020 and was completed in May 2021.

Click here to view the construction notice.

This project proposes building an additional passenger loading platform and tracks to improve Metrolink service and extending the existing pedestrian bridge for added elevator and stair access.

Environmental studies and final design are under way and are expected to be completed by 2022.

Click here to view the project fact sheet. 

This project is modernizing elevators at the Corona-North Main and Riverside-Downtown Stations by upgrading parts and installing new technology. The upgrades will allow the elevators to run more smoothly and with less down-time or needed repairs.

Upgrades to the Corona-North Main Station elevators were completed in April 2020. Upgrades to the Riverside-Downtown Station elevators are expected to be completed in June 2020.

Click here for the construction notice.


Route 91 Pachappa Underpass

Completed Construction

Status: Completed

Location: Western Riverside County

Type of Project: Highways

Location: Route 91 north of Central Avenue in Riverside

Construction: Spring 2020 to October 2021

Investment: $8.8 million (construction)

OVERVIEW

The Riverside County Transportation Commission is building the Route 91 Pachappa Underpass in Riverside. The project will include construction of a retaining wall and removal of part of an overhead railroad bridge. Construction began in April 2020 and was completed in October 2021.

Construction contract was approved at the November 13, 2019 commission meeting.  Work began in April 2020 and was completed in October 2021.

This project includes work that was deleted from the Caltrans Route 91 High Occupancy Vehicle (Carpool Lane) Project. In December 2016, the Commission approved the removal of this work from that project and authorized this separate Pachappa Underpass Project. Most of the work consists of removing the Pachappa Underpass temporary bridge and its associated retaining walls and building a new retaining wall to support the final Union Pacific Railroad alignment.


15/91 Express Lanes Connector

Completed Construction

1123 ELC Map Legend web

Status: Completed

Location: Corona

Type of Project: Express Lanes

Location: Interstate 15 and Route 91, Corona

Construction: April 2021 to November 2023

Investment: $270 million

OVERVIEW

RCTC, in partnership with Caltrans, constructed the 15/91 Express Lanes Connector, linking the 15 Express Lanes to the 91 Express Lanes. The project provides a new connection from the eastbound 91 Express Lanes to the northbound 15 Express Lanes and from the southbound 15 Express Lanes to the westbound 91 Express Lanes.

The 15/91 Express Lanes Connector was designed to provide a seamless transition between these Riverside County tolling systems for reliable, convenient travel for residents of Corona, Norco, Jurupa Valley, Eastvale, and points north in San Bernardino County, as well as express buses. The project also extended both the eastbound 91 outside general purpose lane and the eastern end of the 91 Express Lanes approximately one-half mile east to Promenade Avenue to help with vehicle merging in this area.

Project benefits and features include:

  • Reduce congestion and improve traffic operations
  • Enhance safety
  • Create a seamless transition and increase travel time reliability between these two tolled systems

The project is fully funded, and RCTC awarded a design-build contract in April 2020. Construction began in April 2021 and the new connector opened to motorists in November 2023.

Construction began in April 2021 and the new connector opened in November 2023. During construction, four single-direction weekend closures of the connectors were utilized, as well as periodic nighttime lane closures of the connectors and on Route 91.

Week of March 25, 2024

Week of March 13, 2024

Week of February 13, 2024

Week of February 5, 2024

Week of January 29, 2024

Week of January 22, 2024

Week of January 15, 2024

Week of January 8, 2024

Week of January 2, 2024

Week of December 25, 2023

Week of December 18, 2023

Week of December 11, 2023

Week of December 4, 2023

Week of November 27, 2023

Special Construction Update, 15/91 ELC Now Open! – November 21, 2023

Week of November 20, 2023

Week of November 13, 2023

Week of November 6, 2023

Week of October 30, 2023

Week of October 23, 2023

Week of October 16, 2023

Week of October 9, 2023

Week of October 2, 2023

Week of September 29, 2023

Week of September 11, 2023

Week of September 5, 2023

Week of August 28, 2023

Week of August 21, 2023

Week of August 14, 2023

Week of July 31, 2023

Week of July 24, 2023

Week of July 17, 2023

Week of July 10, 2023

Week of July 3, 2023

Week of June 26, 2023

Week of June 19, 2023

Week of June 12, 2023

Week of June 5, 2023

Week of May 29, 2023

Week of May 22, 2023

Week of May 15, 2023

Week of May 8, 2023

Week of April 24, 2023

Week of April 10, 2023

Week of April 3, 2023

Week of March 27, 2023

Week of March 20, 2023

Week of March 13, 2023

Week of March 6, 2023

Week of February 27, 2023

Week of February 20, 2023

Week of February 13, 2023

Week of February 6, 2023

Week of January 30, 2023

January 27, 2023

Week of January 23, 2023

Week of January 16, 2023

Week of January 9, 2023

Week of January 3, 2023

Week of December 19, 2022

Week of December 12, 2022

Week of December 5, 2022

Week of November 28, 2022

Week of November 21, 2022

Week of November 14, 2022

Week of October 24, 2022

Week of October 17, 2022

Week of October 10, 2022

Week of September 26, 2022

Week of September 19, 2022

Week of September 12, 2022

Week of September 5, 2022

Week of August 29, 2022

Week of August 22, 2022

Week of August 8, 2022

Week of August 1, 2022

July 22, 2022

Week of July 15, 2022

Week of July 8, 2022

Week of July 1, 2022

Week of June 27, 2022

Week of June 20, 2022

Week of June 13, 2022

Week of June 6, 2022

Week of May 31, 2022

Week of May 23, 2022

Week of May 16, 2022

Week of May 9, 2022

Week of May 2, 2022

Week of April 15, 2022

Week of April 11, 2022

Week of April 4, 2022

Week of March 21, 2022

Week of March 7, 2022

Week of February 28, 2022

Week of February 21, 2022

Week of February 14, 2022

Week of February 7, 2022

January 30, 2022 – Special Alert, Westbound 91 Now Open

Week of January 17, 2022

Week of January 10, 2022

Week of January 3, 2022

Week of December 27, 2021

Week of December 20, 2021

Week of December 13, 2021

Week of December 6, 2021

Week of November 29, 2021

Week of November 22, 2021

Week of November 15, 2021

Week of November 8, 2021

Week of November 1, 2021

Week of October 25, 2021

Week of October 18, 2021

Week of October 11, 2021

Week of October 4, 2021

Week of September 27, 2021

Week of September 20, 2021

Week of September 13, 2021

Week of September 6, 2021

Week of August 30, 2021

Week of August 23, 2021

Week of August 9, 2021

Week of August 2, 2021

Week of July 26, 2021

Week of July 19, 2021

Week of July 5, 2021

Week of July 12, 2021

Week of July 5, 2021

Week of June 28, 2021

Week of June 21, 2021

Week of June 14, 2021

Week of May 31, 2021

Week of May 24, 2021

Week of May 17, 2021

Week of May 10, 2021

Week of May 3, 2021

Week of April 26, 2021

Week of April 19, 2021

  • 2017: RCTC receives $180 million in funding from Senate Bill 132 and the Commission approves amending existing contracts and/or pursuing new contracts to expedite project delivery
  • 2018: RCTC prepares preliminary design and environmental studies
  • 2019: Commission approves funding gap by authorizing the allocation of $90 million from surplus toll revenue and staff begins procurement for a design-build contractor
  • April 2020: Commission approves design-build contractor and design work begin in spring 2020
  • April 2021: Construction begins
  • November 2023: Connector opens

ENVIRONMENTAL DOCUMENTS

Environmental Impact Report/Environmental Impact Statement (EIS/EIR):

The Supplemental Project Report and Environmental Revalidation documents were approved in June 2019:

The 15/91 Express Lanes Connector will require a nighttime full closure of southbound 15, from Hidden Valley Pkwy to the 91, Sunday, October 22 from 12 midnight to 7 a.m.


INTERSTATE 15 RAILROAD CANYON ROAD INTERCHANGE PROJECT

INTERSTATE 15 RAILROAD CANYON ROAD INTERCHANGE PROJECT

RCTC I15/Railroad Canyon Interchange Project Map Graphic

Status: Completed

Location: Western Riverside County

Type of Project: Interchanges

Location: Interstate 15 Railroad Canyon Road, Lake Elsinore

Construction: May 2020 to summer 2022

Investment: $41 million (construction)

OVERVIEW

The Riverside County Transportation Commission, in partnership with Caltrans and the City of Lake Elsinore, upgraded the Interstate 15 Railroad Canyon Interchange in Lake Elsinore.

The project was built to address the needs of the area’s growing number of residents and recreational visitors. The project also was designed to improve traffic flow for people traveling to and from Canyon Lake. Benefits and features included:

  • Safety: Built auxiliary lanes on I-15 to help drivers enter and exit the highway and reduce traffic back-ups
  • Capacity: Added two new lanes on Railroad Canyon Road through the interchange and new lanes to the on-ramps and off-ramps with I-15
  • Traffic Flow: Replaced the northbound diamond off-ramp with hook-style on– and off-ramps that both connect to Grape Street
  • Cleaner Air: Reduced the number of idling vehicles waiting to enter/exit I-15, for improved air quality
  • Access: Constructed sidewalks and bike lanes along Railroad Canyon Road

 Construction began in May 2020 and the new interchange opened in April 2022. Project closeout work continued through summer 2022.

Construction began in May 2020 and the new interchange opened in April 2022. Project closeout work continued through summer 2022.

  • 2000: City of Lake Elsinore and Caltrans conducted a Project Study Report. Five alternatives and a no-build alternative were approved in the PSR in 2003.
  • 2006: A Value Analysis Study was performed to evaluate each alternative.
  • 2008: A Traffic Impact Analysis Study was completed, which identified four traffic scenarios. An Alternative Reduction Workshop was held and three alternatives were advanced for further study. The Federal Highway Administration provided suggestions to improve two alternatives, and in 2009, the City of Lake Elsinore and Caltrans eliminated the third remaining alternative.
  • 2013: City of Lake Elsinore requested that RCTC manage the project on its behalf.
  • 2017: Caltrans released the Draft Environmental Document. After comments were received, Caltrans selected Alternative 2, which consisted of construction of the interchange with hook ramps at Grape Street. The Federal Highway Administration approved the project’s Finding of No Significant Impact.
  • May 2018: RCTC received the balance of project funding through the California Transportation Commission’s allocation of $15 million in gas tax revenue; project became fully funded.
  • May 2018-2020: Right of way acquisition
  • October 2019: Final design completed
  • March 2020: Construction contract awarded
  • May 2020: Construction began
  • July 2021: Presentation to Lake Elsinore City Council – One year milestone
  • April 2022: New interchange opened ahead of schedule

For questions related to the I-15 Railroad Canyon Interchange Project, please email info@rctc.org.


Route 91 Corridor Operations Project

Completed Construction

Riverside County Transportation Commission Projects SR-91 Project Content Image

Status: Completed

Location: Western Riverside County

Type of Project: Highways

Location: Westbound Route 91, Green River Road on-ramp to Route 241

Construction: From November 2020 to February 2022

Investment: Estimated $29 million for construction

OVERVIEW

The Riverside County Transportation Commission, in partnership with Caltrans, the Orange County Transportation Authority, the City of Corona and the Transportation Corridor Agencies, opened the new westbound 91 lane between Green River Road in Corona and the 241 Toll Road in Anaheim on January 6, 2022. This new lane was the centerpiece of the Route 91 Corridor Operations Project. RCTC led the project through construction.

The project added a new lane to westbound 91 for approximately two miles between the Green River Road on-ramp and the southbound Route 241 connector, next to the outer shoulder. The new lane is designed to help relieve westbound traffic congestion through this heavily traveled corridor, particularly for morning commuters.

 

RCTC, in conjunction with project partners, opened on the new lane on January 6, 2022.

Construction began in November 2020. The new lane opened January 6, 2022.

Week of March 7, 2022 – Revised

Week of March 7, 2022

Week of February 28, 2022

Week of February 23, 2022

Week of February 14, 2022 – Revised

Week of February 14, 2022

Week of February 7, 2022

Week of January 31, 2022

Week of January 24, 2022

Week of January 17, 2022 – REVISED

Week of January 17, 2022

Special Construction Update – January 6, 2022

Week of January 3, 2022

Week of December 27, 2021

Week of December 20, 2021

Week of December 13, 2021

Week of December 6, 2021

Week of November 29, 2021

Week of November 22, 2021

Week of November 15, 2021

Week of November 8, 2021 (Revised)

Week of November 8, 2021

Week of November 1, 2021

Week of October 25, 2021

October 20, 2021, Narrow Lanes Special Construction Update

Week of October 18, 2021

Week of October 11, 2021

Week of October 4, 2021

Week of September 27, 2021

Week of September 20, 2021

Week of September 13, 2021

Week of September 6, 2021

Week of August 30, 2021

Week of August 23, 2021

Week of August 16, 2021

Week of August 9, 2021

Week of August 4, 2021

Week of July 26, 2021

Week of July 19, 2021

Week of July 12, 2021

Week of July 5, 2021

Week of June 28, 2021

Week of June 21, 2021

Week of June 14, 2021

Week of June 7, 2021

Week of May 31, 2021

Week of May 24, 2021

Week of May 17, 2021

Week of May 10, 2021

Week of May 3, 2021

Week of April 26, 2021

Week of April 19, 2021 Revised

Week of April 19, 2021

Week of April 12, 2021

Week of April 5, 2021

Week of March 29, 2021

Week of March 22, 2021

Week of March 15, 2021

Week of March 8, 2021 (Extended)

Week of March 8, 2021

Week of February 22 and March 1, 2021

Week of February 8, 2021

Week of February 1, 2021

Week of January 19, 2021

Full westbound freeway closure – January 15, 2021

Week of January 11, 2021

Weeks of December 21 & 28, 2020

Week of December 14, 2020

Week of December 7, 2020

Week of November 30, 2020

Week of November 23, 2020

Week of November 16, 2020

Week of November 9, 2020

  • March 2017: RCTC opens new general-purpose lanes and the 91 Express Lanes as part of the 91 Project on March 20.
  • February–April 2018: RCTC gathers data related to traffic conditions to evaluate mobility on the 91 corridor. RCTC evaluates several options, including recommendations from the public, to improve traffic flow.  Operational improvements to the 91 Express Lanes, including changes in striping, signage and channelizers, are initiated. 
  • May 2018: Commission votes to expend surplus 91 Express Lanes revenue to implement the 91 Corridor Operations Project, including:
    • Restriping of the northbound I-15 entrance to the 91 Express Lanes,
    • Restriping of westbound 91 at the Riverside/Orange County Line entrance/exit of the 91 Express Lanes,
    • Studying the Green River Road on-ramp meter, and
    • Conducting project development for environmental approvals and final design for the addition of a westbound 91 additional lane from the Green River Road on-ramp to the southbound State Route 241 connector, and conducting a traffic and revenue study for the westbound additional lane, with a return to the Commission in fall 2018 with recommendations. 
  • June 2018 and September 2018: Caltrans conducts two field studies, in which the ramp meter is temporarily turned off at the westbound 91 Green River Road Interchange.
  • September 2018: Crews restripe northbound I-15 entrance to 91 Express Lanes
  • November–December 2018:  Crews restripe westbound 91 at the Riverside/Orange County Line entrance/exit of the 91 Express Lanes. Commission receives report of ramp meter study and opts to keep ramp meter in place and receives results of a traffic and revenue study and cost estimates for the westbound 91 additional lane. Commission votes to continue environmental studies and final design for the westbound 91 additional lane, with direction to return to the Commission at a future date to determine funding options and priorities.
  • November 2019: RCTC and agency partners in Orange County and at Caltrans reach agreement on set of high priority improvement projects on Route 91 and Route 241 to reduce traffic congestion, including the 91 Corridor Operations Project.
  • April 2020: Commission adopts Environmental Revalidation
  • May 2020: RCTC awards construction management contract
  • August 2020: RCTC to present construction contract to Commission for approval
  • November 2020: Construction began on phase 1
  • January 6, 2022: RCTC opens new westbound 91 lane between Green River Rd. and the 241 Toll Road

For questions related to the 91 Corridor Operations Project, please email info@rctc.org


Route 60 Truck Lanes

Completed Construction

Photo of the State Route 60 current lanes and the future condition after the truck lanes are completed.

Status: Completed Construction

Location: Western Riverside County

Type of Project: Highways

Location: State Route 60 between Gilman Springs Road to 1.4 miles west of Jack Rabbit Trail, unincorporated Riverside County

Construction: July 2019 to Summer 2022

Investment: $138.4 Million; $113 Million in Construction Costs

Jobs Created: 2,491

OVERVIEW

RCTC, in partnership with Caltrans, widened a 4.5-mile section of Route 60 from Gilman Springs Road to 1.4 miles west of Jack Rabbit Trail in Riverside County’s Badlands between Moreno Valley and Beaumont. The project was within mountainous terrain with a curving alignment and steep grades. The project was designed to improve safety and efficiency of travel between the Coachella Valley and western Riverside County.  Click here to view project videos. 

Project features included:

  • Constructing an eastbound truck climbing lane
  • Constructing a westbound truck descending lane
  • Widening shoulders to standard widths – 12-foot exterior shoulders and 11-foot interior shoulders
  • Establishing two wildlife crossings and placing wildlife fencing
  • Improving motorist sight distance by flattening roadway curves

Project construction will occur from June 2019 to summer 2022. Please see the Construction Updates and the Shifting Gears newsletter below for project progress.

The $113 million construction investment is funded by a combination of state, federal and local sources, including Measure A, the voter-approved half-cent sales tax for transportation improvements in Riverside County.

Construction will take place from June 2019 to summer 2022. View the schedule and staging exhibits from open houses held in June 2019.

  • June 2014: Caltrans issues the Final Initial Study with Mitigated Negative Declaration/Environmental Assessment with Finding of No Significant Impact.
  • October 2015: Caltrans issues the Recirculated Initial Study with Proposed Mitigated Negative Declaration/Environmental Assessment.
  • November 2015: Caltrans hosts public hearing for the Recirculated Initial Study with Proposed Mitigated Negative Declaration/Environmental Assessment.
  • May 2016: RCTC approves the Environmental Impact Report and is challenged in state court by a group of plaintiffs.
  • June 2018: RCTC resolves litigation for project – Click here for more information.
  • June 2018: RCTC begins advertising for construction management services.
  • October 2018: RCTC begins advertising for construction bids.
  • December 2018: RCTC awards contract for construction management services.
  • January 2019: RCTC awards construction contract.
  • August 2019 – March 2020: Six month westbound lane closure to complete the project  one year earlier than originally planned.
  • Summer 2022 – Anticipated opening of new lanes.

Week of September 2, 2024

Week of August 26, 2024

Week of August 12, 2024

Week of August 5, 2024

Week of July 29, 2024

Week of April 22, 2024

Week of March 25, 2024

Week of March 18, 2024 (POSTPONED)

May 12, 2023

May 5, 2023

Week of April 10, 2023

Week of February 13, 2023

Week of February 6, 2023

Week of July 11, 2022

Week of June 27, 2022

Week of June 20, 2022

Week of June 6, 2022

Week of May 30, 2022

Week of May 16, 2022

Week of May 9, 2022

Week of May 2, 2022

Week of April 25, 2022

Week of April 18, 2022

April 16, 18-20, 2022

Week of April 4, 2022

Week of March 21, 2022

Week of March 14, 2022

Week of March 7, 2022

Week of February 28, 2022

Week of February 21, 2022

Week of February 14, 2022

Week of February 7, 2022

Week of January 31, 2022

Week of January 24, 2022

Week of January 17, 2022

Week of January 10, 2022

Week of January 3, 2022

Week of December 20, 2021

Week of November 29, 2021

Week of November 1, 2021

Week of October 25, 2021

Week of October 18, 2021

Week of October 11, 2021

Week of September 20, 2021

Week of September 13, 2021

Week of September 6, 2021

Week of August 30, 2021

Week of August 23, 2021

Week of August 16, 2021

Week of August 9, 2021

Week of August 2, 2021

Week of July 26, 2021

Closure – July 22 – August 13, 2021

Week of July 19, 2021

Week of July 12, 2021

Week of July 5, 2021

Week of June 28, 2021

Week of June 21, 2021

Week of June 14, 2021

Week of June 7, 2021

Week of May 31, 2021

Week of May 24, 2021

Week of May 17, 2021

Week of May 10, 2021

Week of May 3, 2021

Week of April 26, 2021

Week of April 19, 2021

Week of April 12, 2021

Week of April 5, 2021

Closure – March 29, 2021

Week of March 29, 2021

Week of March 22, 2021

Week of March 15, 2021

Week of March 8, 2021

Week of March 1, 2021

Week of February 22, 2021

Week of February 15, 2021

Week of February 8, 2021

Week of February 1, 2021

Week of January 25, 2021

Week of January 18, 2021

Week of January 11, 2021

Week of January 4, 2021

Week of December 21, 2020

Full Weekend Closure – January 8, 2021

Week of December 14, 2020

Week of December 7, 2020

Week of November 30, 2020

Week of November 23, 2020

Week of November 16, 2020

Week of November 9, 2020

Week of November 2, 2020

Week of October 26, 2020

Week of October 19, 2020

Week of October 12, 2020

Week of October 5, 2020

Week of September 28, 2020

Week of September 21, 2020

Week of September 14, 2020

Week of September 7, 2020

Week of August 31, 2020

Week of August 24, 2020

Week of August 17, 2020

Week of August 10, 2020

Week of August 3, 2020

Week of July 27, 2020

Week of July 20, 2020

Week of July 13, 2020

Week of July 6, 2020

Week of June 29, 2020

Week of June 22, 2020

Week of June 15, 2020

Week of June 8, 2020

Week of June 1, 2020

Week of May 25, 2020

Week of May 18, 2020

Week of May 11, 2020

Week of May 4, 2020

Week of April 27, 2020

Week of April 20, 2020

Week of April 13, 2020

Week of April 6, 2020

Week of March 30, 2020

Week of March 23, 2020

Week of March 16, 2020

Week of March 2, 2020

Week of February 24, 2020

Week of February 17, 2020

Week of February 10, 2020

Week of February 3, 2020

Week of January 27, 2020

Week of January 20, 2020

Week of January 13, 2020

Week of January 6, 2020

Week of December 23, 2019

Week of December 16, 2019

Week of December 9, 2019

Week of December 2, 2019

Week of November 25, 2019

Week of November 18, 2019

Week of November 11, 2019

Week of November 4, 2019

Week of October 28, 2019

Week of October 21, 2019

Week of October 14, 2019

Week of October 7, 2019

Week of September 30, 2019

Week of September 23, 2019

Week of September 16, 2019

Week of September 9, 2019

Week of September 2, 2019

Week of August 26, 2019

Week of August 19, 2019

Week of August 12, 2019

Week of August 5, 2019

Week of July 29, 2019

Week of July 22, 2019

Week of July 15, 2019

Week of July 8, 2019

Week of July 1, 2019

Week of June 24, 2019

Week of June 17, 2019

Week of June 10, 2019

Photos:

Videos:

Environmental Documents

    • Initial Study with MND / Environmental Assessment with FONSI, click here.
    • Recirculated IS/EA, click here.
    • Superseded DED (also referenced as original IS/EA), click here.

For questions related to the 60 Truck Lanes Project, please email info@rctc.org.


Riverside-La Sierra Metrolink Station Improvements

Completed Construction

La Sierra Metrolink Station Parking Lot Expansion Project Image

Status: Completed

Location: Western Riverside County

Type of Project:  Rail Station Improvements

Location: Riverside – La Sierra Metrolink Station

Construction: April 2018 to January 2019

OVERVIEW

RCTC expanded the Riverside-La Sierra Metrolink Station at 10901 Indiana Avenue. The project added 442 parking spaces, six bus bays, and a signalized access/driveway onto Indiana Avenue. The expansion occurred on an adjacent 4.69-acre vacant lot owned by RCTC and includes Park & Ride facilities northeast of the station.

Construction began in April 2018 and will be complete in October 2018.