Project Status
Under Construction
Overview
Widen six miles of the SR-91 between Adams Street and the 60/91/215 Interchange by constructing one HOV lane in each direction, closing the existing HOV gap.
Construction Start
Spring 2012
Construction End
2015
Investment
$248 million
Jobs Created
4,469
Lead Agency
Caltrans
Route(s) Affected:

Roadway Improvements

  • Relocate 9th Street westbound on ramp to 10th Street
  • Braid eastbound and westbound ramps at 14th Street and University Avenue
  • Modifications to Arlington interchange
  • Widen and reconstruct Madison eastbound on and off ramps and Central westbound off ramp

Bridge Replacements

  • 14th Street
  • Cridge Street
  • Pachappa Railroad
  • Ivy Street

Widen Existing Bridges

  • Central Avenue
  • Arlington Avenue
  • Brockton Avenue/Mary Street
  • Madison Street
  • Jefferson Street
  • SR-91 HOV Project map